The development projects

BRUNFAUT (The Factory)

Rue Brunfaut and Rue Fin, 1080 Molenbeek

Works on the Brunfaut site are progressing according to plan. The project is a residential complex of 93 apartments, 66 parking spots and 1,443 m² of office space. Techniques and inside finishings are ongoing. The project is expected to be delivered in the course of the second quarter of 2020. In addition, and in agreement with the municipality of Molenbeek, the adjacent square “Place d’Or” will also be totally refurbished.

Meyers-Hennau

Rue Meyers-Hennau 5-17, 1020 Brussels

The structural works of the project Meyers-Hennau are completed up to the ground floor. Completion of the project, comprising 37 apartments, 11 houses and 51 parking spots, is expected in the fourth quarter of 2020.

JOURDAN

Rue Jourdan 1060 Saint-Gilles

The building permit for the development of a building located rue Jourdan (rue Jourdan 95 in 1060 Saint-Gilles) is ongoing. Works to remove asbestos have also started recently.

MTC2

Avenue Marcel Thiry in Woluwe-Saint-Lambert

The preparatory works for the Marcel Thiry C2 project have started at the end of 2019. Soil and land preparation works are starting in the course of the first quarter of 2020. The project comprises 42 apartments.